A lien on the improved property
A recorded, timely claim of lien attaches to the real property itself. For lienors not in privity with the owner, the total of all liens under one direct contract generally cannot exceed the contract price.
Florida construction attorneys
Florida's lien statute rewards the party that served the right notice on the right day. We work out which dates you have met, which you have missed, and what claim is still open.
Construction payment disputes
Money owed for construction work can be collected through a lien, a payment claim, or a contract suit, and each has its own paperwork and clock.
A contractor who dealt directly with the owner, a subcontractor hired by that contractor, and a supplier to the subcontractor stand in different positions under Chapter 713, Florida Statutes. Privity with the owner decides which notices you owed.
The same statute protects owners. A lien claimed by someone who never served a required notice, or who recorded late, may be one the owner can defeat. We read the payment chain from the owner down, whichever end you stand on.
Before the dates pass
Payment claims are built from a handful of dates and documents. Gather them while everyone can still be found.
Lien deadlines run from when you started and when you last furnished labor, services or materials. Pull daily logs, delivery tickets and emails that show both dates.
Owners generally record a notice of commencement before work starts. It names the owner, the contractor, any surety on a payment bond and the lender, which tells you who to serve and who else may pay.
Gather the contract, change orders, pay applications, invoices, lien waivers and any Notice to Owner with proof of delivery. Keep every waiver you signed, dated and complete.
List which amounts the other side admits it owes and which it contests. Florida's payment statute treats undisputed sums differently from contested ones.
What a payment claim can reach
A construction lien, a claim under the payment statute, and a contract suit can each be available at once.
Pursuing one route does not always close the others, and the lien statute describes itself as cumulative to other existing remedies.
A recorded, timely claim of lien attaches to the real property itself. For lienors not in privity with the owner, the total of all liens under one direct contract generally cannot exceed the contract price.
A person who supplied labor, services or materials may file a verified complaint about undisputed amounts unpaid more than 30 days, and seek an accounting, an injunction or attachment against the person who received payment, to the extent of the undisputed amount.
The right to sue for breach of the written agreement remains, and the prevailing party in a lien enforcement action or bond claim is entitled to a reasonable attorney's fee under the lien statute.
How the lien statute works
Chapter 713 makes the lien a creature of paperwork. Miss a step and the right can be lost, however clear the debt.
For a lienor not in privity with the owner, Section 713.06, Florida Statutes, requires a Notice to Owner served before starting work or within 45 days after starting, and in any event before the owner's final payment following the contractor's final affidavit. Failing to serve it, or serving it late, is stated to be a complete defense to enforcement of the lien. Laborers are excepted from that notice. Under Section 713.08, the claim of lien must be recorded no later than 90 days after final furnishing of labor, services or materials. Under Section 713.22, the lien does not last more than one year after recording unless an action to enforce it is filed in that time.
Chapter 713, Part I
Four questions decide most lien and payment fights before anyone discusses the merits.
How we work
Owed money or being liened, we read the documents against the statute and choose the route first.
Talk with our teamA simpler way forward
You do not need to know whether your lien is valid before you call. Bring what you have, even if it is incomplete.
Who hired whom, what was built, what was paid, and what is still owed.
We tell you which notices and dates look intact and what remains available.
If you retain us, fees are discussed at the consultation and structured as no fee unless we recover. We handle the filings and the deadlines.
Payment dispute questions
What applies to you depends on where you sit in the chain and on the dates.
Ask us about your situation ↗It is a written notice that a lienor not in privity with the owner, other than a laborer, serves on the owner to perfect lien rights. Under Chapter 713, it must generally go out before work starts or within 45 days after starting. Late or missing notice can be a complete defense to the lien.
The statute says the claim may be recorded during the work or afterward, but not later than 90 days after the lienor's final furnishing of labor, services or materials. Termination of the original contract can shorten that period in some situations.
Yes, in time. A lien does not continue longer than one year after recording unless an action to enforce it is commenced. An owner can also serve a notice of contest that cuts the time to sue to 60 days. Recording alone does not collect the money.
Sometimes. The lien statute is described as cumulative to other remedies, so a claim on the contract may remain even where the lien is lost. Section 95.11 generally allows five years on a written contract and four on other contracts, with shorter periods for some claims, such as one year for payment-bond claims.
Not necessarily. A lien right cannot be waived in advance, and a waiver can reach only labor, services or materials already furnished. The wording, the date stated and what was paid in exchange all matter.
Proof and further reading
Case resultWe won $80K+ for homeowners stuck with a defective solar system, canceling their finance deal, refunding payments, and fixing their roof.
Read the case →
Case resultWe won $50K for a client injured on Hollywood Boardwalk after a construction crew failed to provide proper safety measures for pedestrians.
Read the case →